Network Analysis

What exactly is a project?

PM 1 – I am directing a team of research scientists. We are running trials on a new analgesic drug on behalf of a pharmaceutical company.

• It is my responsibility to design the experiments and make sure that proper scientific and legal procedures are followed, so that our results can be subjected to independent statistical analysis.

• A new drug

PM 2- The international aid agency which employs me is sending me to New Delhi to organize the introduction of multimedia resources at a teachers’ training college.

• My role is quite complex. I have to make sure that appropriate resources are purchased- and in some cases developed within the college.

• I also have to encourage the acceptance of these resources by lecturers and students within the college.

A new method of teaching students

Project

• A project is a temporary Endeavour involving a connected sequence of activities and a range of resources,

• which is designed to achieve a specific and unique outcome and

• which operates within time, cost and quality constraints and

• Which is often used to introduce change?

“A project is a series of activities directed to accomplishment of a desired objective.”

Plan your work first…..then work your plan

Characteristic of a project:-

l A unique, one-time operational activity or effort

l Requires the completion of a large number of interrelated activities

l Established to achieve specific objective

l Resources, such as time and/or money, are limited

l Typically has its own management structure l Need leadership

Examples

– constructing houses, factories, shopping malls, athletic stadiums or arenas

– developing military weapons systems, aircrafts, new ships

– launching satellite systems

– constructing oil pipelines

– developing and implementing new computer systems

– planning concert, football games, or basketball tournaments

– Introducing new products into market.

What is project management?

• The application of a collection of tools and techniques to direct the use of diverse resources towards the accomplishment of a unique, complex, one time task within time, cost and quality constraints.

• Its origins lie in World War II, when the military authorities used the techniques of operational research to plan the optimum use of resources.

One of these techniques was the use of networks to represent a system of related activities.

Work break down structure

Project can be splitted into small tasks with sequence of their execution. This process is known as work break down structure “

A method of breaking down a project into individual elements (Components, subcomponents, activities and tasks) in a hierarchical structure which can be scheduled and cost.

It defines tasks that can be completed independently of other tasks, facilitating resource allocation, assignment of responsibilities and measurement and control of the project. It is foundation of project planning. It is developed before identification of dependencies and estimation of activity durations. It can be used to identity the tasks in the CPM and PERT

clip_image002

Network Representation

Each activity of the project is represented by an arc pointing in the direction of progress in the project.

The nodes of the network establish the precedence relationships among the different activities of the project.

Network analysis

• Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects.

Network is a graphical representation of all the Activities and Events arranged in a logical and sequential order. • Network analysis plays an important role in project management.• A project is a combination of interrelated activities all of which must be executed in a certain order for its completion.

Main objectives are:

Complete the project within stipulated period..

Optimize resources utilization.

Better coordination in interdependent activities.

C.P.M & P.E.R.T are two methodologies to analyze the network

A flow-chart that illustrates;

The order in which tasks will be performed

Dependencies between tasks

Use of nodes and arrows

 

Arrows An arrow leads from tail to head directionally

Indicate ACTIVITY, a time consuming effort that is required to perform a part of the work.

Comprise three elements Nodes/ Event

  • A node is represented by a circle

Indicate EVENT, a point in time where one or more activities start and/or finish.

Signals the beginning or ending of an activity

Designates a point in time Represented by a circle (node)

Span time –

the actual calendar time required to complete an activity Network

Shows the sequential relationships among activities using nodes

and arrows.

It is the combination of all activities and events define the project and the activity precedence relationships.

Activity

A task or a certain amount of work required in the project Requires time to complete

Represented by an arrow Activity is the actual performance of the job. This consumes resources (Time, human resources, money, and material)

• PERT and CPM are the two most popular network analysis technique used to assist managers in planning and controlling large scale projects.

• PERT- (Programme Evaluation Review Technique)

• CPM - (Critical Path Method)

Applications: -

Construction of a Residential complex, Commercial complex,

Petro-chemical complex Ship building

Satellite mission development

Installation of a pipe line project etc...

Predecessor activity: An activity that must occur before another activity.

Successor activity: An activity that must occur after another activity.

An activity can be in any of these conditions:

It may have a successor(s) but no predecessor(s) - starts a network It may have a predecessor(s) but no successor(s) - ends a network It may have both predecessor(s) and successor(s) - in the middle of a network

clip_image004

Rules to draw the network

Each event is presented by the nodes.

Each activity is represented by one, and only one (arc) arrow.

Each activity must be identified by two distinct end nodes.

clip_image006

Activity A has two end nodes:

1- start node, 2 – end node

Rules to draw the network

Rule-1 –

An activity (succeeding) cannot start unless all its preceding activities have been

completed. (not applicable on dummy activity)

clip_image008

A must finish before either B or C can start

clip_image010

both A and B must finish before C can start A must finish before B can star

both A and C must finish before D can start.

clip_image012

Rule-2:- There should be no loops in the project network.

clip_image014

Rule-3:- Each events should have a distinct number. Usually number at the head of the arrow is greater than that at its tail. (Fulkerson’s Rule)

ie., numbers should not be duplicated.

Fulkerson’s Rule

The starting event (having no predecessor activity is numbered as 1 ) other events are numbered in increasing order from 1 to rightwards

,if there are more then 1 initial event found in a diagram , anywhere they are to be numbered from top to bottom in increase order. No two events can have the same number in any case.

Rule-4 :

Not more than one activity can have the same preceding and succeeding events. OR No two events can be connected by more than one activity.

Rule-4- (Concurrent Activities)

clip_image016

Rule-5

• Network diagram cannot have more than one starting node or end node.

• The activities emerging from event 1 should have no predecessor activities & event having highest number in diagram should have no successor activity.

Example-1

image

image

Useof dummy activity:

• To establish correct precedence relationships, dummy activities are used.

• A dummy activity, which is normally depicted by a dashed arc, consumes no time or resources.

• For example, if two activities that can start concurrently and have the same duration can be represented using a dummy activity as:

• A dummy activity is an imaginary activity which can be accomplished in zero time and which does not consume resources.

• It may also be used to represent a constraint.{ It Indicates only precedence relationships . Does not require any time of effort}

image

To maintain the correct precedence relationships, the following questions must be answered as each activity is added to the network:

(a) What activities must immediately precede the current activity?

(b) What activities must follow the current activity?

(c) What activities must occur concurrently with the current activity?

The answers to these questions may require the use of dummy activities to ensure correct precedence among the activities.

Problem 1

1. Construct the project network consisting of activities A to L with the following precedence relationships:

(a) A, B and C, the first activities of the project, can be executed concurrently.

(b) A and B precede D.

(c) B precedes E, F and H.

(d) F and C precede G.

(e) (e) E and H precede I and J.

(f) (f) C, D, F and J precede K.

(g) (g) K precede L.

(h) (h) I, G and L are the terminal activities of the

(i) project.

Ans:-

image

image

Problem 2

Construct the project network consisting of activities A to I with the following precedence relationships:

(a) A and B, the first activities of the project start immediately.

(b) A and B precede C.

(c) B precedes D and E.

(d) A and B precede F.

(e) F and D precede G and H.

(f) C and G precede I.

(f) E, H and I are terminal activities

Ans

image

Problem 3

• a) Activities (1-2) and (1-3) can start simultaneously.

• b) Activity (1-2) proceeds activity (2-4) and (2-6)

• c) Activities (3-4) and (3-5) can start only on completion of activity

• (1-3).

• d) Activity (4-7) can start only after (2-4) and (3-4) have been

• completed.

• e) Activities (5-7) and (5-9) can not start till activities (2-4), (3-4) and

• (3-5) are completed.

• f) Activities (6-8) and (6-7) can start only on completion of (2-6).

• g) Activity (8-9) follows activity (6-8).

• h) Activities (8-9), (7-9) and (5-9) can be taken up simultaneously for

• completion of the project.

Historical Evolution.( PERT & CPM)

Before 1957 there was no generally accepted procedure to aid the management of a Project. In 1958 PERT was developed by team of engineers working on a Polaris Missile programme of the navy. This was a large project involved 250 prime contractors and about 9000 job contractors. It had about 19 million components. In such projects it is possible that a delay in the delivery of a small component might hold the progress of entire project. PERT was used successfully and the total time of completion was reduced from 7 years to 5 years.

In 1958 Du Pont Company used a technique called Critical Path Method (CPM) to Schedule and control a very large project like overhauling of a chemical plant, there by reducing the shutdown period from 130hrs to 90 hrs saving the company 1 million dollar.

Both of these techniques are referred to as project scheduling techniques.

Determining the Project Schedule

• Some activities can be done simultaneously so project duration should be less than 25 weeks

Critical path analysis is used to determine project duration

• The critical path is the longest path through the network

Critical Path Analysis

Need to find the following for each activity:

• Earliest Start Time (EST)

• Earliest Finish Time (EFT)

• Latest start time (LST)

• Latest Finish Time (LFT)

Activity Slack

• Each event has two important times associated with it :

• Earliest time , Te , which is a calendar time when a event can occur when all the predecessor events completed at the earliest possible times

• Latest time , TL , which is the latest time the event can occur with out delaying the subsequent events and completion of project.

• Difference between the latest time and the earliest time of an event is the slack time for that event

• Positive slack : Slack is the amount of time an event can be delayed without delaying the project completion.

Forward Pass

• Identifies earliest times (EST and EFT)

• EST Rule: All immediate predecessors must be done before an activity can begin

• If only 1 immediate predecessor, then EST = EFT of predecessor

• If >1 immediate predecessors, then EST = Max {all predecessor EFT’s}

EFT Rule: EFT = EST + activity time

image

Backward Pass

• Identifies latest times (LST an LFT)

• LFT Rule:

– If activity is the immediate predecessor to only 1 activity, then LFT = LST of immediate follower

– If activity is the immediate predecessor to multiple activities, then LFT = Min {LST of all imm. followers}

LST Rule: LST = LFT – activity time

Backward Pass: Latest Start and Finish Times

image

image

Slack Time and Critical Path(s)

• Slack is the length of time an activity can be delayed without delaying the project Slack = LST – EST

• Activities with 0 slack are Critical Activities

• The Critical Path is a continuous path through the network from start to finish that includes only critical activities.

• Is that the sequence of activities and events where there is no “slack” i.e..

Zero slack.

• Longest path through a network

• minimum project completion time

Total Slack Time vs. Free Slack Time

• Total slack time is shared by more than 1 activity

• Example: A 1 week delay in activity B will leave 0 slack for activity D

• Free slack time is associated with only 1 activity Example: Activity F has 6 week of free slack time

Problem-1. The following table lists the activities of a maintenance project .

image

image

Problem

image

Solution : The Flaws are

• i) The activity B and E have same initial and ending nodes , which is not correct.

• ii) a loop is formed by activities j,k and l , WHICH IS NOT PERMITTED.

• iii) The dummy activity d2 is unnecessary

Problem

image

Solution :

image

Problem :

Information on the activities required for a project is as follows

• Draw the network and calculate

• The Earliest start (ES), earliest Finish (EF), latest start (LS),

• latest finish(LF) and TF times of each of the activities.

image

Comments

Popular posts from this blog

DUALITY THEORY:THE ESSENCE OF DUALITY THEORY

NETWORK OPTIMIZATION MODELS:THE MINIMUM SPANNING TREE PROBLEM

INTEGER PROGRAMMING:THE BRANCH-AND-CUT APPROACH TO SOLVING BIP PROBLEMS